Hi!
For the Exam, is Duration calculated as

EF-ES = Duration or
EF-ES +1 = Duration?
I used #1 on a trial test question and got it wrong. I see it both ways in various presentations and learning tools.

Calculating Duration on a Network Diagram 8 years 7 months ago #12281

  • Tracy Shagnea, PMP
  • Tracy Shagnea, PMP's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 134
  • Karma: 7
  • Thank you received: 46
Maryann,

It depends on the method used to create the network diagram. Check out Cornelius' response here:

https://www.project-management-prepcast.com/kunena/pmp-exam-discussion/3099-cpm-calculations-start-with-day-0-or-day-1

Best wishes,

Tracy
Forum Moderator
PMP, CSM, M.S. Management
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login