fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Probability and impact matrix

Probability and impact matrix 6 years 6 months ago #12204

  • Anil Gidwani
  • Anil Gidwani's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 25
  • Thank you received: 0
The PMBOK Guide shows the P&I matrix as an output of the Plan Risk Management process. I believe that this must of necessity be an empty matrix, since no risks have been identified yet at that point.

Further downstream, the PMBOK Guide states that the P&I matrix is an input to the Perform Qualitative Risk Analysis process as part of the Risk Management Plan. It also says: "If it is not available, it may be developed during the Perform Qualitative Risk Analysis process".

Isn't there some confusion here regarding when the P&I matrix is first created? Why does the PMBOK guide list it in Plan Risk Management when it will by default be unpopulated then? Why is the P&I matrix not an unequivocal output of the Perform Qualitative Risk Analysis process? Am I missing a point here?

Probability and impact matrix 6 years 6 months ago #12212

  • Christoph Farrenkopf
  • Christoph Farrenkopf's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
Sorry, but there is not shown in The PMBOK Guide the P&I matrix as an output of the Plan Risk Management process ! Are you referring according PMBOK Guide 5th edition or to another PMBOK edition ?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login