Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Procurement risk contradiction (head first vs RITA)

Procurement risk contradiction (head first vs RITA) 3 years 10 months ago #9507

  • Lawrence Li
  • Lawrence Li's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 4
In Head First book,a question as follows

Which of the following contracts has the MOST risk for the buyer?
A. Cost plus fixed fee (CPFF)
B. Time and materials (T&M)
C. Cost plus award fee (CPAF)
D. Fixed price (FP)

Ans is B

But according to RITA, the T&M risk is just medium , C is the answer.....

I think I believe RITA is better for this case?
Attachments:
The following user(s) said Thank You: Hasan El-Hasan

Procurement risk contradiction (head first vs RITA) 3 years 10 months ago #9645

  • Lawrence Li
  • Lawrence Li's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 4
Any idea?

Procurement risk contradiction (head first vs RITA) 3 years 9 months ago #9836

  • James Anderson
  • James  Anderson's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 1
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login