fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Procurement risk contradiction (head first vs RITA)

Procurement risk contradiction (head first vs RITA) 7 years 3 months ago #9507

  • Lawrence Li
  • Lawrence Li's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 4
In Head First book,a question as follows

Which of the following contracts has the MOST risk for the buyer?
A. Cost plus fixed fee (CPFF)
B. Time and materials (T&M)
C. Cost plus award fee (CPAF)
D. Fixed price (FP)

Ans is B

But according to RITA, the T&M risk is just medium , C is the answer.....

I think I believe RITA is better for this case?
Attachments:
The following user(s) said Thank You: Hasan El-Hasan

Procurement risk contradiction (head first vs RITA) 7 years 2 months ago #9645

  • Lawrence Li
  • Lawrence Li's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 4
Any idea?

Procurement risk contradiction (head first vs RITA) 7 years 2 months ago #9836

  • James Anderson
  • James  Anderson's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 1
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login