Which of the following contracts has the MOST risk for the buyer?
A. Cost plus fixed fee (CPFF)
B. Time and materials (T&M)
C. Cost plus award fee (CPAF)
D. Fixed price (FP)
Ans is B
But according to RITA, the T&M risk is just medium , C is the answer.....