Reply: Procurement risk contradiction (head first vs RITA)

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Procurement risk contradiction (head first vs RITA)

Max. showing the last 6 posts - (Last post first)
7 years 1 month ago #9836

James Anderson

James  Anderson's Avatar

7 years 2 months ago #9645

Lawrence Li

Lawrence Li's Avatar

Any idea?
7 years 3 months ago #9507

Lawrence Li

Lawrence Li's Avatar

In Head First book,a question as follows

Which of the following contracts has the MOST risk for the buyer?
A. Cost plus fixed fee (CPFF)
B. Time and materials (T&M)
C. Cost plus award fee (CPAF)
D. Fixed price (FP)

Ans is B

But according to RITA, the T&M risk is just medium , C is the answer.....

I think I believe RITA is better for this case?