Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: OLIVER LEHMAN (75 QUESTIONS)

OLIVER LEHMAN (75 QUESTIONS) 2 months 2 weeks ago #8343

  • Maria EUgenia Labajos
  • Maria EUgenia  Labajos's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 5
  • Karma: 0
Hello everybody!

Could someone explain the following question to me? It´s from Oliver Lehman 75 questions and I don´t understand why the first option is the correct one (I hope you can see the network diagram).

You have just created the following network logic diagram to describe the planned flow of activities for your project which will start tomorrow:



Which potential inconsistency in the diagram should you solve right now to ensure that the activities and the milestones "Start" and "A-F finished" are correctly linked?

Activity E is open ended (a "dangle") in relation to the finish milestone path convergence.
Activity F is open ended in relation to the path divergence after the start milestone.
You cannot calculate a critical path when lags and/or leads are calculated in percent.
Activities E to F need another task drawn as a hammock to calculate level of effort.

Thanks in advance and best regards,
Mª. Eugenia Labajos

OLIVER LEHMAN (75 QUESTIONS) 2 months 2 weeks ago #8393

  • Ganavel Dorai Rethinam, MSc, PMP
  • Ganavel Dorai Rethinam, MSc, PMP's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 16
  • Thank you received: 6
  • Karma: 0
Hi Maria,

I read in another forum and this is what was explained.
"Relationship can be in % which means based on x% of predecessor the successor can start/finish depending on type of relationship. However, you cannot calculate critical path when relationship are in % and not absolute duration (e.g. days)".

Based on this explanation, the best choice would be C. But the answer given online is A.

OLIVER LEHMAN (75 QUESTIONS) 2 months 2 weeks ago #8397

  • Maria Eugenia Labajos
  • Maria Eugenia Labajos's Avatar
Thank you, Ganavel.
I also thought that C was the correct answer, but I got confused with the given solution.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®