fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Time management- need help

Time management- need help 8 years 4 months ago #6563

  • Vivek Gupta
  • Vivek Gupta's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
refrence- Exam central

Activity A has a finish to finish relation ship with Activity B. Activity A has a duration of 7 days. Activity B has a duration of 5 days with 3 days lag. what is the total duration of activity A and B?

1) Day 12

2) Day 9

3) Day 7

4) Day 8

Can somebody explain me why Option D

Time management- need help 8 years 4 months ago #6566

  • KHALED MKAREM
  • KHALED MKAREM's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 3
Hello Vivek,

Since the relationship is Finish - to - Finish, The activity (B) has duration of 5 days with 3 days Lag. The total duration for activity (B) is 8 days. However, activity (A) has 7 days duration which is less than Activity B. Thus the total duration for both activities is 8 days.

Best way to understand the scenario is to draw two nodes namely A and B and draw the relationship between them, you will be able to figure it out as I did :)
The following user(s) said Thank You: Vivek Gupta

Time management- need help 8 years 4 months ago #6567

  • KHALED MKAREM
  • KHALED MKAREM's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 3
Hello Vivek,

Since the relationship is Finish - to - Finish. The activity ( B ) has duration of 5 days + 3 days Lag = 8 Days. However, The activity ( A ) has 7 days duration which is less than the total of activity ( B ). Thus, the total duration for both activities is 8 days.

The best thing to do is, draw two nodes with its relationship and you will figure out what is the correct answer for such scenario as I did :)
The following user(s) said Thank You: Vivek Gupta

Time management- need help 8 years 4 months ago #6568

  • Tracey South
  • Tracey South's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 131
  • Karma: 6
  • Thank you received: 27
HI Vivek:

Remember that finish-to-finish relationships don't require that both tasks be completed simultaneously. It just means that the first task be finished, in order for the second task to finish. The second task can finish any time after the first task finishes.

Tracey
Community Moderator
The following user(s) said Thank You: Vivek Gupta
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login