When do bidder conferences normally take place?

After the contract has been awarded to keep alternatives open.
After submission of bid or proposal, but before contract award.
Prior to the submission of a bid or proposal by the bidder.
After technical meetings with bidders to discuss contract requirements.

Answer : 3

I understood that Seller proposals are given as input to Conduct procurement process & so the choice would be 2nd. But the answer was 3rd as per PMBOK. Please help me to understand this concept.

Regards
Narayan

Bidder Conference 8 years 7 months ago #6035

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1981
  • Karma: 118
  • Thank you received: 604
Narayan,

Please always include a reference where you found a question. So... can you please tell us where you found this one?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Bidder Conference 8 years 7 months ago #6036

  • Narayan
  • Narayan's Avatar Topic Author
  • Visitor
  • Visitor
Hi Cornelius,

This was from oliver Lehmann 75 questions.

Regards,
Narayan

Bidder Conference 8 years 7 months ago #6038

  • Puneet Singh
  • Puneet Singh's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 0
Procurement Documents-RFP, RFQ, RFB,RFI - are created and ready to be sent after completing plan procurement management.
Bidder Conference is performed with Prospective sellers before they can send proposals and for better understanding of SOW
Procurement documents are sent and responses(sellers) are received after bidder conference.

As a rule, please don't understand the order of inputs mentioned in PMBOK5 Process(Inputs) as sequence, rather you should focus on tool and techniques using inputs.

Bidder Conference 8 years 7 months ago #6043

  • Rahul Kakkar
  • Rahul Kakkar's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 161
  • Karma: 9
  • Thank you received: 56
In addition to what Puneet said, project management bidders conferences are part of the process of selecting vendors provide goods or services to the project. The request for proposal (RFP) that is sent out to potential sellers/ vendors contains information about a meeting to be held prior to the submission of the seller bid/proposal.
,
Rahul Kakkar, PMP, MBA
Community Moderator


How are we doing? Your opinion matters. To help us improve, please check out our survey at www.surveymonkey.com/s/pmpexamforum

Bidder Conference 8 years 7 months ago #6044

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
Hello Narayan,

below is the definition from the PMBOK guide. think of it as a clarification session so that sellers can understand what is required and they can submit their proposals to match the requirements. so it has to done before the submittal of proposals.

"12.2.2.1 Bidder Conferences
Bidder conferences (sometimes called contractor conferences, vendor conferences, and pre-bid conferences)
are meetings between the buyer and all prospective sellers prior to submittal of a bid or proposal. They are used
to ensure that all prospective sellers have a clear and common understanding of the procurement requirements),
and that no bidders receive preferential treatment."
Ahmed Amin Abdullah, PMP
Community Moderator

Bidder Conference 8 years 7 months ago #6056

  • Narayan
  • Narayan's Avatar Topic Author
  • Visitor
  • Visitor
Hi All,

Thanks for your inputs. Take away is 2 important points for me.

1. RFP will cover the meeting information.
2. Only after the meeting, procurement documents will be sent out to prospective sellers.

Regards
Narayan

Bidder Conference 8 years 7 months ago #6057

  • Puneet Singh
  • Puneet Singh's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 0
Hi Narayan,

Just on your Point 2:
  • Send Procurement Documents
  • Complete bidder conference
  • Receive response from seller (Seller Proposals)
  • Analyze seller proposals using Proposal Evaluation Techniques( Derived from Source Selection criteria)
  • Use Independent Estimates if needed
  • Arrange for Negotiations
  • Award Contract

Bidder Conference 8 years 7 months ago #6062

  • Todd Hammer
  • Todd Hammer's Avatar Topic Author
  • Visitor
  • Visitor
It helps to sit back and look at the whole picture too, putting yourself in other people's shoes. If you are the vender that is to bid on the project, you might have questions in order for you to create an accurate estimate. These answers are given in the bidder conference, BEFORE you give the quote.

Bidder Conference 4 years 7 months ago #18118

  • nicole dallon
  • nicole dallon's Avatar Topic Author
  • Visitor
  • Visitor
I agree that this is very confusing. I know the process everyone is including in their answers from hands on experience but the way the Plan Procurement section is written is very confusing. i have the Velocitech book. i would answer these questions incorrectly trying to follow the prep materials.

- seller proposal are inputs to Conduct Procurement and a bidder conference is a tool to get to the contract. misleading
- independent estimates are outputs of Plan Procurement Management but used after the seller proposals are received. again misleading.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login