Hi all,
Can you guide me deciding best answer for below question?
PM is managing software development project where one of stakeholder needs to make change that will affect the budget. PM follows the procedure to implement the change. Which of the following must get updated to reflect the change?
A. Project Management Plan
B. Project Cost Baseline
C. Cost Change control system
D. Project performance reviews
I chose option A as BEST answer, thinking that the change approved will change Scope baseline, schedule baseline and of course cost baseline as budget is affected too. Also other subsidiary plans of Project Management plan also need to be updated, such Risk Management plan, Quality Management plan etc. As all of these are part of Project Management Plan, I chose Answer A.
But the simulator gave Answer B as correct answer.
Can you please give your thoughts?
Thanks,
ND