fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Best answer for the question

Best answer for the question 8 years 8 months ago #5989

  • Nishant Desai
  • Nishant Desai's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 12
  • Thank you received: 1
Hi all,

Can you guide me deciding best answer for below question?

PM is managing software development project where one of stakeholder needs to make change that will affect the budget. PM follows the procedure to implement the change. Which of the following must get updated to reflect the change?

A. Project Management Plan
B. Project Cost Baseline
C. Cost Change control system
D. Project performance reviews


I chose option A as BEST answer, thinking that the change approved will change Scope baseline, schedule baseline and of course cost baseline as budget is affected too. Also other subsidiary plans of Project Management plan also need to be updated, such Risk Management plan, Quality Management plan etc. As all of these are part of Project Management Plan, I chose Answer A.

But the simulator gave Answer B as correct answer.

Can you please give your thoughts?

Thanks,
ND

Best answer for the question 8 years 8 months ago #5991

  • Tracey South
  • Tracey South's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 131
  • Karma: 6
  • Thank you received: 27
Hi ND:

For questions like these, I would approach this by working with the facts. We can't assume that the change will affect scope or schedule. Since we only know that the budget will be affected, the cost baseline needs to be updated. Answer B.

An example of this may be that a contractor's renewal included a rate increase. Nothing changes in terms of scope or timing. Just the budget is impacted.

Tracey
Community Moderator

Best answer for the question 8 years 8 months ago #5994

  • Dawn Upperman
  • Dawn Upperman's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 116
  • Karma: 4
  • Thank you received: 19
Hi Nishant, I agree with Tracey, the budget would be impacted for sure.
Last edit: by Dawn Upperman. Reason: spelling

Best answer for the question 8 years 8 months ago #5995

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Nishant -- can you please also tell us where you found this question, so as to give credit to the original question creator?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Best answer for the question 8 years 8 months ago #5996

  • Nishant Desai
  • Nishant Desai's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 12
  • Thank you received: 1
Hi,

I found this question in book called "Head First PMP". It was under section of sample exercise in Cost Management knowledge area.

Thanks.
The following user(s) said Thank You: Cornelius Fichtner

Best answer for the question 8 years 8 months ago #6001

  • Puneet Singh
  • Puneet Singh's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 13
  • Thank you received: 0
Think of this request where a stakeholder has submitted a change request to purchase safety equipment for your workers. That change will only affect Cost Baseline.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login