fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Project management plan updates vs. Change request

Project management plan updates vs. Change request 8 years 10 months ago #5616

  • Monica Merito
  • Monica Merito's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Hi,

Maybe someone can help me with the following questions.

Control processes have project management plan updates and change requests as separate outputs. The former feeding into the Develop project management plan process and the latter into Perform integrated change control (cf. PMBOK Guide data flow diagrams). However “Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process” (cf. PMBOK Guide 5th Edition 4.2.3.1 Project Management Plan). On the other hand, since plans are progressively elaborated, once a control process identifies the need for revising a knowledge area plan, it can trigger an iteration of the respective planning process (e.g. the Control communications process can trigger an iteration of the Plan communications management process).

- Why two separate outputs?
- Why do plan updates not go through Perform integrated change control?
- In what process(es) are plans actually updated?
- In what process(es) are stakeholders informed of the updates?

Thank you

Monica

Project management plan updates vs. Change request 8 years 10 months ago #5618

  • Michael DeCicco
  • Michael DeCicco's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 130
  • Karma: 12
  • Thank you received: 44
Monica
Why two separate outputs? Why do plan updates not go through Perform integrated change control?
- If I am looking accurately from your perspective, you are saying that you see develop project management plan output as part of PICC, so why is it really two outputs.

- The change request process reviews proposed changes that the project team agree require formal approval. The result of the approved change request may not affect, in each case, a need to update the project management plan.

- In what process(es) are plans actually updated? p.63 PMBOK 5th Edition. Implement approved changes to achieve the project's objectives in Direct and Manage Project Work.
- In what process(es) are stakeholders informed of the updates? p.63 PMBOK 5th Edition, In general, communicate disposition of change request in PICC. Specifically, you'll update them during manage stakeholders using your stakeholder management plan and the communication methods identified from the communication plan.

How are we doing? Your opinion matters. To help us improve, please check out our survey at www.surveymonkey.com/s/pmpexamforum
Yours Respectfully
Michael DeCicco, PMP
Community Moderator

Project management plan updates vs. Change request 8 years 10 months ago #5619

  • Michael DeCicco
  • Michael DeCicco's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 130
  • Karma: 12
  • Thank you received: 44
correction: methods identified in the Stakeholder Management Plan described in 13.2.3.1 p. 403

How are we doing? Your opinion matters. To help us improve, please check out our survey at www.surveymonkey.com/s/pmpexamforum
Yours Respectfully
Michael DeCicco, PMP
Community Moderator

Project management plan updates vs. Change request 8 years 1 week ago #7219

  • Leon Shao
  • Leon Shao's Avatar
  • Visitor
  • Visitor
The question is about the output of the processes in Monitoring & Controlling group.
Given the project management plan is approved, the change (or update) from the controlling processes should ONLY go through Perform Integrated Change Control.
What kind of change is treated as UPDATE and not required PICC?

Project management plan updates vs. Change request 7 years 4 months ago #9086

  • Shadab hussain
  • Shadab hussain's Avatar
  • Visitor
  • Visitor
Im searching for the answer of same question. Also why we have pmp update in output of develop schedule? Thats the only process in planning which generates pmp plan update aa output

Project management plan updates vs. Change request 6 years 9 months ago #11012

  • Muhammad
  • Muhammad's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Simple question!

Do project management plan updates, project document updates, OPA / EEF updates also go through Perform Integrated Change Control or not?

Project management plan updates vs. Change request 11 months 3 weeks ago #30453

  • Daniel
  • Daniel's Avatar
  • Visitor
  • Visitor
Dear Monica, your question happened to be an answer to my question of whether updates to the project management plan mean updating it right away without going through DPP
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login