Monica
Why two separate outputs? Why do plan updates not go through Perform integrated change control?
- If I am looking accurately from your perspective, you are saying that you see develop project management plan output as part of PICC, so why is it really two outputs.
- The change request process reviews proposed changes that the project team agree require formal approval. The result of the approved change request may not affect, in each case, a need to update the project management plan.
- In what process(es) are plans actually updated? p.63 PMBOK 5th Edition. Implement approved changes to achieve the project's objectives in Direct and Manage Project Work.
- In what process(es) are stakeholders informed of the updates? p.63 PMBOK 5th Edition, In general, communicate disposition of change request in PICC. Specifically, you'll update them during manage stakeholders using your stakeholder management plan and the communication methods identified from the communication plan.
How are we doing? Your opinion matters. To help us improve, please check out our survey at
www.surveymonkey.com/s/pmpexamforum