fbpx

Reply: Form Your own Question!

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Form Your own Question!

Max. showing the last 6 posts - (Last post first)
9 years 5 months ago #4663

Abhirup Banerjee

Abhirup Banerjee's Avatar

Let me start with one Time Management Question

If A Task A needs to be started 10 days before TASK B is started, Which of the following relations are true?

1>They have Start to Start relationship, with 10 day lead on Task A
2>They have Start to Finish relationship with 10 day lag on Task B
3>They have Start to Start relationship, with 10 day lag on Task B
4>Both 1 and 3 are True

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login