TOPIC: Form Your own Question!

Form Your own Question! 4 years 10 months ago #4663

  • Abhirup Banerjee
  • Abhirup Banerjee's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Thank you received: 3
Let me start with one Time Management Question

If A Task A needs to be started 10 days before TASK B is started, Which of the following relations are true?

1>They have Start to Start relationship, with 10 day lead on Task A
2>They have Start to Finish relationship with 10 day lag on Task B
3>They have Start to Start relationship, with 10 day lag on Task B
4>Both 1 and 3 are True
IMPOSSIBLE Itself says I M POSSIBLE
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on August 24/25 for just $179. Click to learn more... OR Click to watch a free session...