4 years 4 months ago #18919

Mukhwana

's Avatar

@Ivan Fućak, thank you very much for that answer. 4 years later and your answer is sitll helping out folks. Much appreciated!
6 years 6 months ago #11818

Anonymous

's Avatar

So how to solve this problem?
6 years 9 months ago #10997

Aditi Kapoor

's Avatar

I didn't understand y it is 5.2 days also what's the logic behind this.
SD=P-O/6
Could you please explain?
7 years 4 months ago #8926

Hazem Ibrahim

Hazem Ibrahim's Avatar

please note that putting ±3 sigma precision level in the question is meaningless and useless it is just to scatter you away
7 years 4 months ago #8918

shravan

's Avatar

Waw...Super..I got it...thanks a lot...dint understand logit behind t ...but doesnt matter
7 years 8 months ago #7772

Mohammed Yaseen

's Avatar

For +_ 3 Sigme, the standard deviation = 3 * Standard Deviation of 1 Sigma prceision level.

So in this case, the standard deviation should be = 3 * 5.19 = 15.57

Hope, I am right.
If not, PLEASE explain me.