fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Why is this the correct answer?

Why is this the correct answer? 9 years 7 months ago #4589

  • SANDHYARANI P BHIDE
  • SANDHYARANI P BHIDE's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 1
Hi,

I don't understand how this answer was calculated for the question from Oliver Lehmann's free 75 question test.
Can anyone please enlighten? The correct answer is B ie. approx. 5.2 days.

27. A project manager made 3-point estimates on a critical path and found the following results: (Check attached table below)

Assuming ±3 sigma precision level for each estimate, what is the standard deviation of the allover path?

(A) App. 4.2 days
(B) App. 5.2 days
(C) App. 6.2 days
(D) You can not derive the path standard deviation from the information given.
Attachments:

Why is this the correct answer? 9 years 5 months ago #4774

  • Ivan Fućak
  • Ivan Fućak's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
You can use following link for calculation:
www.firebrandtraining.co.uk/learn/pmp/co...e-activity-durations
You have to calculate standard deviation for each activity.
(24-12)/6=2,
(14-8)/6=1,
(27-15)/6=2,
28-10)/6=3,
(35-17)/6=3
Variances of each activities are squares of deviations of activities.
Stand.deviation of path is square root of sum of variances:
SQRT(4+1+4+9+9)=SQRT(27)=5,19

Why is this the correct answer? 7 years 9 months ago #7772

  • Mohammed Yaseen
  • Mohammed Yaseen's Avatar
  • Visitor
  • Visitor
For +_ 3 Sigme, the standard deviation = 3 * Standard Deviation of 1 Sigma prceision level.

So in this case, the standard deviation should be = 3 * 5.19 = 15.57

Hope, I am right.
If not, PLEASE explain me.

Why is this the correct answer? 7 years 5 months ago #8918

  • shravan
  • shravan's Avatar
  • Visitor
  • Visitor
Waw...Super..I got it...thanks a lot...dint understand logit behind t ...but doesnt matter

Why is this the correct answer? 7 years 5 months ago #8926

  • Hazem Ibrahim
  • Hazem Ibrahim's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 58
  • Thank you received: 2
please note that putting ±3 sigma precision level in the question is meaningless and useless it is just to scatter you away

Why is this the correct answer? 6 years 9 months ago #10997

  • Aditi Kapoor
  • Aditi Kapoor's Avatar
  • Visitor
  • Visitor
I didn't understand y it is 5.2 days also what's the logic behind this.
SD=P-O/6
Could you please explain?

Why is this the correct answer? 6 years 7 months ago #11818

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
So how to solve this problem?

Why is this the correct answer? 4 years 5 months ago #18919

  • Mukhwana
  • Mukhwana's Avatar
  • Visitor
  • Visitor
@Ivan Fućak, thank you very much for that answer. 4 years later and your answer is sitll helping out folks. Much appreciated!
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login