fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: What Process Creates the Change Managment Plan?

What Process Creates the Change Managment Plan? 10 years 6 months ago #3792

  • Edward Marciniak
  • Edward Marciniak's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
I have reviewed the PMP Guide 5th ed to see where the Change Management Plan is created ( as an output). It only appears as an input or is included in the outputs as an "update" task. But as we know it is part of the Project Management Plan. However, It does not magically appear. How can you have a document be part of the most important Project Management Plan, be an input to so many processes, if there is no step for creating it? Is this a oversight of PMI? Am I missing something?

What Process Creates the Change Managment Plan? 10 years 6 months ago #3793

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Edward,

The development of the change management plan is not specifically discussed as an activity in the PMBOK Guide. However, it is assumed that it's developed as part of Develop Project Management Plan, where it is listed as one of the components of the PM Plan. (Page 77).

It's the same with the configuration management plan by the way.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: Edward Marciniak, HEMAM RANJIT KUMAR SINGH, Olivia Petiot

What Process Creates the Change Managment Plan? 10 years 4 months ago #3907

  • Scott Gillard
  • Scott Gillard's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 201
  • Karma: 5
  • Thank you received: 29
Is this also the case with the Requirements Management Plan?
Community Moderator

What Process Creates the Change Managment Plan? 10 years 2 weeks ago #4110

  • Arto Pihlaja
  • Arto Pihlaja's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
No, the requirements management plan is explicitly listed as an output of Plan Scope Management.

What Process Creates the Change Managment Plan? 4 years 7 months ago #18301

  • Ali Mouhli
  • Ali Mouhli's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hi All, it seems obviously that the change management plan is part of the OPA and can be used in planing phases.
Best regards
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login