Max. showing the last 6 posts - (Last post first)
10 years 9 months ago #3493

Mohammed Almohimeed

Mohammed Almohimeed's Avatar

Emad, :)

Thanks a lot for detail answer.

Regardas,

Mohammed
10 years 9 months ago #3492

Mohammed Almohimeed

Mohammed Almohimeed's Avatar

Emad,

Thanks a lot for detail answer.

Regardas,

Mohammed
10 years 9 months ago #3491

HUSAM IBRAHIM

HUSAM IBRAHIM's Avatar

If the PM can make great decisions in Matrix organization such as; Generating Project Charter, then it must be Strong Matrix Organization but, it's clear from the question that the organization type is either Week Matrix or balanced Matrix and hence, the PM power will not reach to that level of producing a Project Charter or having it approved.
So, I believe "if this is a real management question!" the PM needs to produce Human resource management plan with clear RAM Stressing on responsibilities, availability of human resources, resource calendar and the reporting structure. The PM should recognize the extent of his power in a Matrix Organization environment.
Getting written commitment on the RAM from the functional managers will reduce the bad effect of duel reporting mechanism.
The bottom line is that, you accept to work in Matrix Organization and it is your Soft skills that will govern your relationship and maximize your power in addition to other skills which might put you in a strong position "power of expert and referent"

Emad Sabri
10 years 9 months ago #3489

Mohammed Almohimeed

Mohammed Almohimeed's Avatar

From PMPBest Yahoo Group sending by PanKaj
10 years 9 months ago #3488

Cornelius Fichtner

Cornelius Fichtner's Avatar

Mohammed,

Please tell us first: Where did you find this question? (We want to make sure that we follow good copyright practices).

Thank you.
10 years 9 months ago #3487

Mohammed Almohimeed

Mohammed Almohimeed's Avatar

A matrix organization begins a new project. Project manager knows that the team is more
responsive to their functional managers than to PM. To overcome this, PM decides to prepare
A) Project plan
B) Project charter
C) Scope statement
D) Human resource management plan

I wait your answer

I think it will be D