Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: EVM question

EVM question 3 years 9 months ago #3169

  • Konstantinos Limas
  • Konstantinos Limas's Avatar
  • Offline
  • Junior Boarder
  • Posts: 25
  • Thank you received: 5
  • Karma: 0
This is a question from PMStudy.com free test.

Question No : 165

You are working on a 12 month assignment to build a website with 4000 pages for $ 1,000,000. You are supposed to spend $ 250,000 every 3 months. After 6 months, you determine that only $ 400,000 of work is completed and cost incurred is $ 800,000. What is the ETC?


Choice 1 $ 2,000,000

Choice 2 $ 1,500,000

Choice 3 $ 1,000,000

Choice 4 1,200,000


Any thoughts?

EVM question 3 years 9 months ago #3174

  • Cathy Schloeder
  • Cathy Schloeder's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 1
  • Karma: 0
$1.2M (4th answer). Calculate the EAC which is 2M and subtract actual cost $800K and you get $1.2M. Good luck.

EVM question 3 years 8 months ago #3187

  • Fadi Sodah
  • Fadi Sodah's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 9
  • Karma: 0
EAC= AC + (BAC-EV)/CPI = $800,000 + ($ 1,000,000 - $ 400,000)/($ 400,000 / $ 800,000) = $ 800,000 + ($ 600,000/0.5) = $ 2,000,000
ETC = EAC – AC = $ 2,000,000 - $ 800,000 = $ 1,200,000

EVM question 3 years 8 months ago #3207

  • Visalakshmi Korrapolu
  • Visalakshmi Korrapolu's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 1
  • Karma: 0
Another way is to directly use (BAC-EV)/CPI without calculating EAC - where Actual Cost is added first and then subtracted.
The following user(s) said Thank You: DINESH SHANMUGAM
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®