fbpx

Reply: EVM question

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : EVM question

Max. showing the last 6 posts - (Last post first)
11 years 1 week ago #3207

Visalakshmi Korrapolu

Visalakshmi Korrapolu's Avatar

Another way is to directly use (BAC-EV)/CPI without calculating EAC - where Actual Cost is added first and then subtracted.
11 years 2 weeks ago #3187

Fadi Sodah

Fadi Sodah's Avatar

EAC= AC + (BAC-EV)/CPI = $800,000 + ($ 1,000,000 - $ 400,000)/($ 400,000 / $ 800,000) = $ 800,000 + ($ 600,000/0.5) = $ 2,000,000
ETC = EAC – AC = $ 2,000,000 - $ 800,000 = $ 1,200,000
11 years 3 weeks ago #3174

Cathy Schloeder

Cathy Schloeder's Avatar

$1.2M (4th answer). Calculate the EAC which is 2M and subtract actual cost $800K and you get $1.2M. Good luck.
11 years 3 weeks ago #3169

Konstantinos Limas

Konstantinos Limas's Avatar

This is a question from PMStudy.com free test.

Question No : 165

You are working on a 12 month assignment to build a website with 4000 pages for $ 1,000,000. You are supposed to spend $ 250,000 every 3 months. After 6 months, you determine that only $ 400,000 of work is completed and cost incurred is $ 800,000. What is the ETC?


Choice 1 $ 2,000,000

Choice 2 $ 1,500,000

Choice 3 $ 1,000,000

Choice 4 1,200,000


Any thoughts?

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login