fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Can you give examples of when a CR is required when the Stakeholder Reg is updat

Can you give examples of when a CR is required when the Stakeholder Reg is updat 3 years 1 month ago #26374

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
As I understand, the stakeholder register does not need a CR if the change does not affect the Project Management Plan. Examples would be changing information on an existing stakeholder. Won't I need a CR when I add or delete a stakeholder because it would change other plans such as Resource Management Plan, possibly the cost baseline if the new stakeholder is a vendor who charges more for their services....

Could you give examples of when a C/R is required and when it would not be required when you update the Stakeholder Register?

Can you give examples of when a CR is required when the Stakeholder Reg is updat 3 years 1 month ago #26378

  • Joe Pang
  • Joe Pang's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 250
  • Karma: 24
  • Thank you received: 98
Hi Sharon, you are correct, the stakeholder register is a project document and does not require a CR to update.

In the example you have given, a new vendor change requires a CR, but it would come from the control procurement process. A stakeholder register update would most likely be one of the action items from an approved CR.

The other possibility is that if you add the stakeholder register to the configuration management plan.

Hope this helps,
Joe
Toronto-based project manager, I specialize in capital construction projects and digital transformation projects for the power & utility sector.

I welcome all types of collaboration opportunities, feel free to connect with me on Linkedin
The following user(s) said Thank You: Sharon S
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login