fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: When would you NOT need a final report?

When would you NOT need a final report? 11 months 2 weeks ago #25352

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
When is a final report not required?

I've seen different responses on practice quizzes but for all of them the project is prematurely terminating yet sometimes the correct answer is write a final report and sometimes it says no final report. I can't tell when a final report is needed if a project prematurely terminates.

When would you NOT need a final report? 11 months 1 week ago #25668

  • Lisa Sweeney PMP
  • Lisa Sweeney PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 113
  • Karma: 13
  • Thank you received: 46
Hi Sharon,

If a project is prematurely terminated and cannot be completed in terms of the activities originally planned, the project manager still has the responsibility to end it appropriately, by performing steps associated in the Closing Process Group. There is value in writing the final report and including the successes and failures of the project, which are useful for a business to understand why the project was terminated, and spells out the procedures for transferring unfinished and finished deliverables and unused materials, depending upon the agreements.

Lisa
The following user(s) said Thank You: Sharon S
Moderators: Yolanda MabutasMary Kathrine PaduaGabriella Dellino, PMPJoe PangJohn Paul BugarinEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMP, PMI-ACPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login