fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Prepcst Quality question

Prepcst Quality question 3 years 3 months ago #25010

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
L08.03: Control Quality - Part 1 at 08:30 of the class. It was if we are not performing to the project plan we need to propose changes. Are they saying instead of trying to meet the requirement, change it? Not sure what changes are we suppose to to propose

Prepcst Quality question 3 years 3 months ago #25060

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 820
  • Karma: 17
  • Thank you received: 114
Sharon, it looks like your question posted 3 times so I’ve deleted the others so you get all the replies in this thread instead of split across three. I took that to mean if you are aware that you can propose changes if it’s not feasible to meet the requirements or the plan, so you can get the project back on track to deliver.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login