fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Timing of kickoff meeting

Timing of kickoff meeting 3 years 7 months ago #23581

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
I want to confirm the timing of the kickoff meeting for PMP exam.

PMBOK guide says it is usually done at the beginning of Planning process group for small projects and at the beginning of Executing process group for large projects.

Rita Mulcahy's book specifies that the kickoff meeting is conducted at the end of Planning group.

I believe what PMBOK guide tells is what we have to follow and considering that the exam usually assumes large projects and matrix organization, kickoff meeting is at the beginning of the Executing process group.

Please confirm. Thank you.
Last edit: by Rahul Vadakke Veetil PMP.

Timing of kickoff meeting 3 years 7 months ago #23584

  • Vani
  • Vani's Avatar
  • Visitor
  • Visitor
TRhe PBOK guide mentions :
1. Kickoff meeting is usually associated with end of planning ( Page 86, PMBOK Sixth edition)
2. Kickoff may occur at different times :
- For smaller projects - its at start of planning phase (since whole team performs planning and execution)
- For some larger projects - the team comes into picture once the whole planning is done. So here the team is usually available only in execution phase. So in this scenario - kick off will take place in execution phase

In my opinion : kick off can take place whenever the team involvement begins.
Its situational.
If nothing is mentioned : then we go with 'usual approach' at end of planning phase

(understanding from Page 86, PMBOK 6th edition)

Timing of kickoff meeting 3 years 6 months ago #23867

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
I did two trial exams. Got it confirmed. For small projects, it is at the beginning of Planning process group. For large projects, it is at the beginning of Executing process group.
The following user(s) said Thank You: Charlie
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login