fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: the challenge of new stakeholder

the challenge of new stakeholder 4 years 3 months ago #23238

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Thank you received: 0
Hi

Could you please clarify this vague point:
A newly identified and critical stakeholder in the execution stage, does not make any change in defined baselines ( scope, time and cost) in this case we should add it just into stakeholder register list or as it is essential as well we should add to the charter as well? also after stakeholder analysis, we found it does not have any effect on baselines it means this change into charter or stakeholder register list or both does not need
CCB approval?

Thanks

the challenge of new stakeholder 4 years 3 months ago #23242

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 819
  • Karma: 16
  • Thank you received: 114
In 'real life' I would simply add them to the stakeholder register.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
The following user(s) said Thank You: Mahdi Seify

the challenge of new stakeholder 4 years 3 months ago #23285

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Thank you received: 0
let me clarify my question:

A newly identified stakeholder in the execution stage does not make any change in defined baselines ( scope, time and cost) and its impact on projecy is high, this conclusion comes after primary analysis,

in this case I should proceed as follow
1. adding to Identified risk list
2.adding stakeholder register list
3. By attaching addendum, add them to the charter
4. advancing stakeholder analysis


is this order currect?
thanks

the challenge of new stakeholder 4 years 2 months ago #23386

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Mahdi,

the project charter very rarely changes in a project life cycle. There should be a very good reason for that; in my opinion a newly identified stakeholder does not look as a very good reason to change the charter. Even though you mention it has a high impact on the project... I think it depends on what this "high" impact implies.
As for the update to the risk register, I would say it may or may not be needed. It depends on whether this newly identified stakeholder brings to newly identified risks.

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Mahdi Seify
Last edit: by Gabriella Dellino, PMP.

the challenge of new stakeholder 4 years 2 months ago #23479

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Thank you received: 0
thanks Gabriella
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login