TOPIC: Workaround

Workaround 5 years 9 months ago #23164

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Karma: 1
  • Thank you received: 0
Hi
Could you please make it clear for me.
Is workaround an unplanned response to Unknown-Unknown or Known-Unknow or both.

Thanks

Workaround 5 years 9 months ago #23171

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Mahdi,

I think workarounds will be needed to deal with an unanticipated problem, so in this respect you may look at it as an "unknown-unknown" that calls for a corrective action to «work around» that problem.
However, what if you have a known-unknown, so the risk has been identified, and possibly accepted (as part of the response strategy), but then it turns out that some corrective action is needed? I would say a workaround would also be needed in this case.

My 2 cents here. I'll be glad to hear what others think about this.

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator

Workaround 5 years 9 months ago #23172

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Karma: 1
  • Thank you received: 0
Could you please other share their thought

Workaround 5 years 9 months ago #23250

  • Kyle Kilbride, PMP
  • Kyle Kilbride, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 121
  • Karma: 7
  • Thank you received: 49
I agree with Gabriella. There's nothing more I can add!
Regards,
Kyle Kilbride, P.Eng, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Mahdi Seify

Workaround 5 years 9 months ago #23262

  • Mansour Ne
  • Mansour Ne's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 1
Hi everyone

I remembered question in real exam talk about workaround
It was long question and ended with this
PM needs to create workaround to deal with?
I remember only two options
1- to deal with risks that passively accepted and/or unidentified risks once it occurs
2- to deal with unidentified risks once it occurs

I got confused during the exam
But Ive chosen No1
I think it was correct

After reaserching for more info
I found the following:
Workaround used for unidentified risks and passively accepted risks

For risk are accepted actively will be dealt with a fallback

Hope this info help you to pass your exam
The following user(s) said Thank You: Mahdi Seify

Workaround 5 years 9 months ago #23283

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Karma: 1
  • Thank you received: 0
Thanks so much, Mansour, It is so helpful
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login