Topic History of : add new risk

Max. showing the last 6 posts - (Last post first)
3 years 7 months ago #23139

Devin

Devin's Avatar

I mean project documents that are generally NOT under configuration management, NOT baselined. The issue log and risk register I call transactional because we are always adding, updating, deleting from them on a daily basis.

Stakeholder register is another project document that can generally be added to at will by the PM.

Hope this helps.
3 years 7 months ago #23137

Mahdi Seify

Mahdi Seify's Avatar

Thanks

What do you mean from transactional non-controlled documents?
3 years 7 months ago #23092

Devin

Devin's Avatar

This risk register, issue log and other transactional non-controlled documents may be added to without a CR.

Hope this helps.
3 years 7 months ago #23087

Mahdi Seify

Mahdi Seify's Avatar

Hi
In Executive phase, if a new risk has been discovered at first we should submit change request or we can directly add to the risk register?

Thanks