fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: add new risk

add new risk 3 years 7 months ago #23087

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Thank you received: 0
Hi
In Executive phase, if a new risk has been discovered at first we should submit change request or we can directly add to the risk register?

Thanks

add new risk 3 years 7 months ago #23092

  • Devin
  • Devin's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 93
  • Karma: 10
  • Thank you received: 52
This risk register, issue log and other transactional non-controlled documents may be added to without a CR.

Hope this helps.
The following user(s) said Thank You: Mahdi Seify

add new risk 3 years 7 months ago #23137

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Thank you received: 0
Thanks

What do you mean from transactional non-controlled documents?

add new risk 3 years 7 months ago #23139

  • Devin
  • Devin's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 93
  • Karma: 10
  • Thank you received: 52
I mean project documents that are generally NOT under configuration management, NOT baselined. The issue log and risk register I call transactional because we are always adding, updating, deleting from them on a daily basis.

Stakeholder register is another project document that can generally be added to at will by the PM.

Hope this helps.
The following user(s) said Thank You: Mahdi Seify
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login