6 years 2 weeks ago #22970

Viswa Kathir

Viswa Kathir's Avatar

Hi,
The answer is 'No' because contingency reserves are part of baselines and hence to use the contingency reserve, change request is not needed.
6 years 2 weeks ago #22967

Sharad Sinha

Sharad Sinha's Avatar

hi, Could some body tell me does 'Change request' is require to access Contingency Reserve?