TOPIC: Does Change request require to access Contingency Reserve?

Does Change request require to access Contingency Reserve? 6 years 1 month ago #22967

  • Sharad Sinha
  • Sharad Sinha's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Karma: 1
  • Thank you received: 0
hi, Could some body tell me does 'Change request' is require to access Contingency Reserve?

Does Change request require to access Contingency Reserve? 6 years 1 month ago #22970

  • Viswa Kathir
  • Viswa Kathir's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 19
  • Karma: 1
  • Thank you received: 5
Hi,
The answer is 'No' because contingency reserves are part of baselines and hence to use the contingency reserve, change request is not needed.
The following user(s) said Thank You: Alexis Higgins
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login