Reply: Change Request to update EEF, OPA and Project Documents

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Change Request to update EEF, OPA and Project Documents

Max. showing the last 6 posts - (Last post first)
3 years 8 months ago #22665

Vivek Sharma

Vivek Sharma's Avatar

BTW did you know that Requirement Management Plan is also known as Business Analysis Plan. :)
3 years 8 months ago #22664

Vivek Sharma

Vivek Sharma's Avatar

Right!
CR is required only for Project Management Plan and it's Components.
Refer Table 4-1 of PMBOK. All 18 Project Management Plan's component , after approval, need CR for modification. The 33 documents mentioned in same table do not need CR.
EEF by definition itself may be outside the authority of Project Manager and/or various stakeholders and hence, of course outside the authority of CCB too.
OPAs also dont need CR.
3 years 8 months ago #22663

Mohammad Farhan Madhwala

Mohammad Farhan Madhwala's Avatar

Hi All, Mine understanding is that UPDATES to EEF, OPA's, Project Documents DO NOT need a change request. Is mine understanding correct ?