TOPIC: Change Request to update EEF, OPA and Project Documents

Change Request to update EEF, OPA and Project Documents 5 years 9 months ago #22663

  • Mohammad Farhan Madhwala
  • Mohammad Farhan Madhwala's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hi All, Mine understanding is that UPDATES to EEF, OPA's, Project Documents DO NOT need a change request. Is mine understanding correct ?

Change Request to update EEF, OPA and Project Documents 5 years 9 months ago #22664

  • Vivek Sharma
  • Vivek Sharma's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Karma: 1
  • Thank you received: 0
Right!
CR is required only for Project Management Plan and it's Components.
Refer Table 4-1 of PMBOK. All 18 Project Management Plan's component , after approval, need CR for modification. The 33 documents mentioned in same table do not need CR.
EEF by definition itself may be outside the authority of Project Manager and/or various stakeholders and hence, of course outside the authority of CCB too.
OPAs also dont need CR.

Change Request to update EEF, OPA and Project Documents 5 years 9 months ago #22665

  • Vivek Sharma
  • Vivek Sharma's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Karma: 1
  • Thank you received: 0
BTW did you know that Requirement Management Plan is also known as Business Analysis Plan. :)
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMP, CSM, DFFS Black BeltElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login