fbpx

Reply: Free PMI-ACP® Exam Sample Question of the Week

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMI-ACP® Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
5 years 3 weeks ago #16723

Ayoor Ola

Ayoor Ola's Avatar

Correct answer is B
5 years 6 months ago #15149

Carlos Piepp

Carlos Piepp's Avatar

Correct answer is B.
5 years 6 months ago #15106

Rachel Madrid

Rachel Madrid's Avatar

Correct Answer: A

Sitting back and observing the team members may be interpreted as a lack of action. However, as a first step, it is important for an experienced agile coach to sufficiently observe the situation.


All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more PMI-ACP® exam sample questions? Just go to free.pm-exam-simulator.com and try the PM Exam Simulator free for 7 days.

OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI). As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.
5 years 6 months ago #15066

SANDIP LANJE

SANDIP LANJE's Avatar

D. Start a coaching session with the team members Since the debate is heated and Team is not able to self-organize As an agile coach need to facilitate team with action to remove impediments which can be done in the retrospective meeting.
5 years 6 months ago #15050

Rachel Madrid

Rachel Madrid's Avatar

Here is our free PMI-ACP® Exam sample question of the week. This question is taken from The PM Exam Simulator at www.pm-exam-simulator.com/pmi-acp

During a retrospective meeting after a failed sprint, emotions run high as the team members blame each other for the failure. Phrases like “He always forgets to check in his code!” or “You never listen to what I have to say!” predominate this heated debate. What is the first thing that an experienced agile coach should do in such a situation?

A. Sit back for a while and observe the team members
B. Intervene immediately to avoid further harm
C. Call in a human resources department representative
D. Start a coaching session with the team members

HINT: The conflict is at its third level, the "Contest". The first action might look counter-intuitive and go against common sense.

Answer will be posted by the end of the week!