TOPIC: PMI-ACP Exam Sample Question of the week

PMI-ACP Exam Sample Question of the week 5 years 10 months ago #14464

  • Rache Madrid
  • Rache Madrid's Avatar Topic Author
  • Visitor
  • Visitor
An agile team used planning poker to estimate user stories. After all team members read a user story, the facilitator asks everyone to choose a card with estimated number of ideal days to complete a user story and then reveal the card. If estimates were widely different, the facilitator would immediately ask for re-estimates until all the estimates converge. What did the facilitator do wrong?

A. Participants used ideal days as the unit for the estimates.
B. Participants re-estimated immediately after everyone revealed their cards.
C. Cards were revealed when the process should have been anonymous.
D. The facilitator did nothing wrong and played by the rules.

Hint: Remember part of the value of planning poker is discussing the estimates.

PMI-ACP Exam Sample Question of the week 5 years 9 months ago #14485

  • Ashish Bang
  • Ashish Bang's Avatar Topic Author
  • Visitor
  • Visitor
Answer is "B"

PMI-ACP Exam Sample Question of the week 5 years 9 months ago #14512

  • Rachel Madrid
  • Rachel Madrid's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
You got it right Ashish! B is the correct answer. Congratulations!

Here is the explanation:
By immediately re-estimating, the team misses out on the benefit of discussing the estimates and why they chose those estimates.


All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more PMI-ACP exam sample questions? Just go to free.pm-exam-simulator.com and try the PM Exam Simulator free for 7 days.

OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI). As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.
The following user(s) said Thank You: TereLyn Hepple, MS, PMP, PSM
Last edit: by Rachel Madrid.