You got it right Ashish! B is the correct answer. Congratulations!
Here is the explanation:
By immediately re-estimating, the team misses out on the benefit of discussing the estimates and why they chose those estimates.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more PMI-ACP exam sample questions? Just go to
free.pm-exam-simulator.com
and try the PM Exam Simulator free for 7 days.
OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI). As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.