fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: PERT PMP Question

PERT PMP Question 6 years 11 months ago #10572

  • Anurag Singh
  • Anurag Singh's Avatar Topic Author
  • Visitor
  • Visitor
Can somebody please provide explanation to the following PERT Question from Oliver Lehmann's free sample questions:
Together with your team, you applied three-point estimation on a critical path which consists of two activities.
The following duration uncertainties are all calculated assuming a ±3sigma confidence interval.
The duration uncertainty—defined as pessimistic minus optimistic estimate—of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths, what is the duration uncertainty of the entire path? 94
o 21 days
o 30 days
o 42 days
o No statement is possible from the information given.

The correct answer is 21 days, but I am not sure how arrive at this answer. Please advise.

PERT PMP Question 5 years 1 month ago #16750

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
First P-O = 18
Second P-O = 24
2P-2O = 42
So, P-O = 21

PERT PMP Question 4 years 5 months ago #19022

  • Jenny
  • Jenny's Avatar Topic Author
  • Visitor
  • Visitor
Can somebody explain this a little bit more? Still not quite understand.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login