Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

At what point are cost and staffing levels highest in the generic project life cycle?

A. At the start of the project
B. When the project work is actually being performed
C. At the close of the project
D. These levels remain even throughout the project

HINT: Cost and staffing levels peak as the actual project work is being performed.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

During the generic project life cycle, generally the cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the project draws to a close.

Free PMP Exam Sample Question of the Week 1 month 1 week ago #8319

  • Kappagomtula
  • Kappagomtula's Avatar
In a real project management cash flow analysis. Both at starting and at close of project heavy cash outflow occurs and during actual execution it is more towards monitoring.

Free PMP Exam Sample Question of the Week 1 month 1 week ago #8320

  • Presal Paclibare
  • Presal Paclibare's Avatar
Moderators: Yolanda Mabutas, Ahmed Amin, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Mark Wuenscher, PMP