At what point are cost and staffing levels highest in the generic project life cycle?
A. At the start of the project
B. When the project work is actually being performed
C. At the close of the project
D. These levels remain even throughout the project
HINT: Cost and staffing levels peak as the actual project work is being performed.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is B.
During the generic project life cycle, generally the cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the project draws to a close.