fbpx

Reply: Free PMP Exam Sample Question of the Week

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMP Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
7 years 6 months ago #8320

Presal Paclibare

's Avatar

Excellent....
7 years 6 months ago #8319

Kappagomtula

's Avatar

In a real project management cash flow analysis. Both at starting and at close of project heavy cash outflow occurs and during actual execution it is more towards monitoring.
7 years 6 months ago #8277

Mary Kathrine Padua

Mary Kathrine Padua's Avatar



Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

At what point are cost and staffing levels highest in the generic project life cycle?

A. At the start of the project
B. When the project work is actually being performed
C. At the close of the project
D. These levels remain even throughout the project

HINT: Cost and staffing levels peak as the actual project work is being performed.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

During the generic project life cycle, generally the cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the project draws to a close.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login