Which of the following buffers are placed at the end of the critical chain to protect the target finish date from slippage?
A. Feeding Buffer
B. Project Buffer
C. Free Buffer
D. Activity Buffer
HINT: This buffer protects the target finish date from moving and is intended to protect the project end date.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is B.
A project buffer is placed at the end of the critical chain to protect the target finish from slippage along the critical chain. On the other hand, feeding buffers are placed at those points in the chain where tasks that are not on the critical path feed into the critical path. Free buffers and activity buffers are not used in critical chain.