fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 8 years 2 weeks ago #7218

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 353
  • Karma: 15
  • Thank you received: 122


Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

Which of the following buffers are placed at the end of the critical chain to protect the target finish date from slippage?

A. Feeding Buffer
B. Project Buffer
C. Free Buffer
D. Activity Buffer

HINT: This buffer protects the target finish date from moving and is intended to protect the project end date.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

A project buffer is placed at the end of the critical chain to protect the target finish from slippage along the critical chain. On the other hand, feeding buffers are placed at those points in the chain where tasks that are not on the critical path feed into the critical path. Free buffers and activity buffers are not used in critical chain.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login