Which of the following processes would you use in a project to reprioritize the remaining work based on resource availability?
A. Control Schedule
B. Develop Schedule
C. Estimate Activity Resources
D. Estimate Activity Durations
HINT: This is usually done in the monitoring and controlling process.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is A.
The Control Schedule Process is used to reprioritize the remaining work in a project. This is done to properly allocate remaining resources based on their availability.