Welcome, Guest
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 10 months 3 weeks ago #6586

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar
  • Offline
  • Administrator
  • Posts: 81
  • Thank you received: 41
  • Karma: 3

Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

Which of the following processes would you use in a project to reprioritize the remaining work based on resource availability?

A. Control Schedule
B. Develop Schedule
C. Estimate Activity Resources
D. Estimate Activity Durations

HINT: This is usually done in the monitoring and controlling process.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is A.

The Control Schedule Process is used to reprioritize the remaining work in a project. This is done to properly allocate remaining resources based on their availability.
The following user(s) said Thank You: Jideofor Ebeogu

Free PMP Exam Sample Question of the Week 10 months 2 weeks ago #6601

  • Anirban Banerjee
  • Anirban Banerjee's Avatar
Great question! Thank you. Anirban
Moderators: Yolanda Mabutas, Ahmed Amin, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Mark Wuenscher, PMP