Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
You have finished estimating costs for your project. What is your next activity with regard to managing the costs?
A. Develop Cost Performance Baseline
B. Develop Work Performance Measurements
C. Develop Budget Forecasts
D. Plan Quality Management
HINT: Determine Budget is the process after the Estimate Costs process.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is A.
The immediate activity following estimation of costs is determining the budget. The output of the Determine Budget process is the development of a Cost Performance Baseline.