The PM PrepCast is closing. All product access ends December 4, 2026.
Until October 31, all products are 50% off.
Read the announcement

NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 10 years 11 months ago #6515

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 589
  • Karma: 18
  • Thank you received: 145


Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

You have finished estimating costs for your project. What is your next activity with regard to managing the costs?

A. Develop Cost Performance Baseline
B. Develop Work Performance Measurements
C. Develop Budget Forecasts
D. Plan Quality Management

HINT: Determine Budget is the process after the Estimate Costs process.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is A.

The immediate activity following estimation of costs is determining the budget. The output of the Determine Budget process is the development of a Cost Performance Baseline.
The following user(s) said Thank You: Jideofor Ebeogu, Cecil D'Souza
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, John Paul Bugarin, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login