fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 8 years 8 months ago #5786

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 349
  • Karma: 15
  • Thank you received: 122


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

Your customer calls you on the phone and informs you of a minor change to a requirement on the project. What is the first thing that should be done?

A. Analyze the request and its consequences to the project
B. Instruct your engineer to implement this minor change
C. Ask the customer to provide a formal change request
D. Note it in the weekly status report

HINT: Changes to requirements must be made formally.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is C.

All changes on a project must be documented and then formally approved via the Perform Integrated Change Control process.
Last edit: by Mary Kathrine Padua.

Free PMP Exam Sample Question of the Week 7 years 11 months ago #7270

  • Sunita Dhoot
  • Sunita Dhoot's Avatar
  • Visitor
  • Visitor
I thought the answer to question #5786 should be A. you need to first analyze the change before asking the customer to submit a formal change request?

Free PMP Exam Sample Question of the Week 6 years 9 months ago #10996

  • Shilpa
  • Shilpa's Avatar
  • Visitor
  • Visitor
The only way you can "FORMALLY" make note of a customer request is by logging a Change Request. So 'C' is correct.

Free PMP Exam Sample Question of the Week 6 years 8 months ago #11100

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
Hello, am struggling with this answer. Does change request happen before analyzing the impacts?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login