TOPIC: Solved Free PMP Exam Sample Question of the Week!

Free PMP Exam Sample Question of the Week! 2 years 9 months ago #5232

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor


Question:
If EV = $100, AC = $90, PV = $110 and BAC = $400, how much is the Cost Variance of a project?

A. $300
B. $40
C. $20
D. $10


Hint: Apply the formula to calculate Cost Variance.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

The formula to calculate Cost Variance (CV) is: CV=EV-AC. Therefore, CV = 100 - 90 = 10.
  • Page:
  • 1
Moderators: Yolanda MabutasAnne BAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonMark Wuenscher, PMPTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Boost Your PMP Exam Prep in Only Six Hours! Join the Live PMP Coaching Class on Dec 02/03 or 16/17 for just $79. Learn More...
The PMP Exam is Changing in 2018
Simona and Cornelius
Free Interview - Listen Now

This interview with Simona Fallavollita (LinkedIn Profile) was recorded at the magnificient Project Management Institute (PMI)® Global Conference 2017 in Chicago, Illinois. We discuss the how, what, why and when of the changes that are coming to the PMP exam.

Thank you!
Cornelius Fichtner, PMP, CSM