NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.
  • Page:
  • 1

TOPIC: Free PMP Exam Sample Question of the Week!

Free PMP Exam Sample Question of the Week! 2 years 2 months ago #5232

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor


Question:
If EV = $100, AC = $90, PV = $110 and BAC = $400, how much is the Cost Variance of a project?

A. $300
B. $40
C. $20
D. $10


Hint: Apply the formula to calculate Cost Variance.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

The formula to calculate Cost Variance (CV) is: CV=EV-AC. Therefore, CV = 100 - 90 = 10.
  • Page:
  • 1
Moderators: Yolanda MabutasAnne BAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonMark Wuenscher, PMPTracy Shagnea, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

×
Join the upcoming PMP Exam Coaching Class with Coach Dan Ryan. 5 Weeks of Live Coaching for just $49. Learn More... 63 students have signed up so far!