Question:
If EV = $100, AC = $90, PV = $110 and BAC = $400, how much is the Cost Variance of a project?

A. $300
B. $40
C. $20
D. $10


Hint: Apply the formula to calculate Cost Variance.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

The formula to calculate Cost Variance (CV) is: CV=EV-AC. Therefore, CV = 100 - 90 = 10.