TOPIC: Free CAPM® Exam Sample Question of the Week

Free CAPM® Exam Sample Question of the Week 3 days 17 hours ago #16243

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 35
  • Thank you received: 4
Assess your readiness and answer this CAPM® Exam Sample Question of the week taken from The CAPM® Exam Simulator

The difference between analogous and parametric estimating is:

A. Analogous estimating uses historical information while parametric estimating is based on expert judgment.
B. Analogous estimating uses historical information while parametric estimating is based on three-point estimating.
C. Analogous estimating uses three estimates to define an activity's cost while parametric estimating uses historical information.
D. Analogous estimating is generally less accurate than parametric estimating.

Hint: Parametric estimating is analogous estimating with considering other variables that reflect the difference between the project and previous ones.

Watch out for the Answer here by the end of the week!
Last edit: by Rachel Madrid.
Moderators: Yolanda MabutasMary Kathrine PaduaDan RyanCynthia Lim Louis, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login