My view is that it depends on the document. Something like the project schedule, which is updated regularly, or the risk and issue registers I wouldn't put through change control because they change too frequently and are working documents. Other documents, like the business case, project charter etc that have formally been approved and form part of the project records about what is authorised to be worked on - those I would put through change control.